To start a procedure for dislocation of an energy facility, please fill out and submit a request (MKAX026) with the Customer Energy Center (CEC) in charge for the metering point in question every business day from 7:30 hrs to 15:30 hrs.
Once the request has been received, an invoice will be drafted and once the customer pays the invoice and submits a proof of payment, an inspection of the location will be performed. Next, a draft-technical decision, alongside with a detailed specification of dislocation costs and a Dislocation Agreement are drafted. Once the Dislocation Agreement has been signed and the costs have been covered by the customer, the dislocation works will start.
Please note that the customer is responsible for obtaining any types of consents and permits from the competent institutions (provided that such documents are required for the completion of the dislocation requested).